Launching in Italy and Greece.

An ear on Europe's grid.

ampear collects what grid operators, regulators and ministries publish about getting projects connected to the grid, and puts it in one place per region, with its history. For a single project, it turns that into a report with a fixed scope: what the queue and curtailment mean for it, and what a battery earns. Every figure links to its source.

What ampear shows for an area

A preview built from real published figures. Switch country and pick a region on the map or with the buttons. You see where the high-voltage grid runs, how much capacity is waiting to connect and how far it has got.

Real published data

  • 380 kV
  • 220 kV
  • Region with published figures

Pick a highlighted region on the map, or use the region buttons. Published figures per region: solar for the three regions with the most solar requests, data centres for the five regions with the most data centre requests. Grid: © OpenStreetMap contributors (ODbL). Boundaries: ISTAT (CC BY 4.0).

Solar connection requests to the transmission grid, 31 August 2026

Requested
36.09 GW852 requests
Cleared by Terna (nulla osta)
18.37 GW432 requests
Ready to build
2.39 GW50 requests

Most requested capacity is not ready to build, yet these requests still hold grid capacity, so new projects are told the grid is full ('virtual saturation'). The decree of 8 September 2026 aims to free that capacity. ampear will track the gap per region, every month.

Solar connection requests to the transmission grid, 31 August 2026

Requested
35.13 GW718 requests
Cleared by Terna (nulla osta)
14.51 GW269 requests
Ready to build
4.56 GW67 requests

Most requested capacity is not ready to build, yet these requests still hold grid capacity, so new projects are told the grid is full ('virtual saturation'). The decree of 8 September 2026 aims to free that capacity. ampear will track the gap per region, every month.

Solar connection requests to the transmission grid, 31 August 2026

Requested
15.38 GW361 requests
Cleared by Terna (nulla osta)
6.37 GW142 requests

Most requested capacity is not ready to build, yet these requests still hold grid capacity, so new projects are told the grid is full ('virtual saturation'). The decree of 8 September 2026 aims to free that capacity. ampear will track the gap per region, every month.

Data centre connection requests to the transmission grid, 31 August 2026

Requested
47.26 GW296 requests
Ready to build
1.68 GW14 requests

Data centres have asked Terna for 101 GW of connections across Italy, almost half of it in Lombardy. Only 15 projects (1.88 GW) are ready to build: 14 in Lombardy and 1 in Piedmont.

Data centre connection requests to the transmission grid, 31 August 2026

Requested
14.52 GW71 requests
Ready to build
0.2 GW1 requests

Data centres have asked Terna for 101 GW of connections across Italy, almost half of it in Lombardy. Only 15 projects (1.88 GW) are ready to build: 14 in Lombardy and 1 in Piedmont.

Data centre connection requests to the transmission grid, 31 August 2026

Requested
5.54 GW24 requests
Ready to build
0 GW

Data centres have asked Terna for 101 GW of connections across Italy, almost half of it in Lombardy. Only 15 projects (1.88 GW) are ready to build: 14 in Lombardy and 1 in Piedmont.

Data centre connection requests to the transmission grid, 31 August 2026

Requested
6.14 GW41 requests
Ready to build
0 GW

Data centres have asked Terna for 101 GW of connections across Italy, almost half of it in Lombardy. Only 15 projects (1.88 GW) are ready to build: 14 in Lombardy and 1 in Piedmont.

Data centre connection requests to the transmission grid, 31 August 2026

Requested
12.45 GW45 requests
Ready to build
0 GW

Data centres have asked Terna for 101 GW of connections across Italy, almost half of it in Lombardy. Only 15 projects (1.88 GW) are ready to build: 14 in Lombardy and 1 in Piedmont.

Pending connection requestsRenewable and storage requests are shrinking as the rules tighten. Data centre demand keeps climbing.
Gigawatt (GW)0100200300400Oct 25Dec 25Feb 26Apr 26Jun 26Aug 26Renewables311.45 GWStorage289.79 GWData centres101.36 GW
Gigawatt (GW)0100200300400Oct 25Apr 26Aug 26Renewables311.45 GWStorage289.79 GWData centres101.36 GW

Month-end totals in GW from Terna's Econnextion, as reported by pv magazine Italia and QualEnergia. Months without a published total are left out. Sources: 1 2 3 4 5 6 7 8 9 10

Show data as a table
MonthRenewables (GW)Storage (GW)Data centres (GW)
Oct 25335.6311.82–
Nov 25334.95311.1468.45
Dec 25328.98308.2669.05
Jan 26326.32309.578.79
Feb 26322.33303.2479.53
Mar 26322.67300.3582.63
Apr 26–––
May 26318.91294.7789.73
Jun 26–––
Jul 26314.2289.8796
Aug 26311.45289.79101.36
Renewable output curtailedWind output curtailed by Terna almost doubled in 2025, from 347.5 to 640 GWh.
Gigawatt-hours (GWh)02004006008002022: 301 GWh30120222023: 300.7 GWh300.720232024: 347.5 GWh347.520242025: 640 GWh6402025
Gigawatt-hours (GWh)02004006008002022: 301 GWh30120222023: 300.7 GWh300.720232024: 347.5 GWh347.520242025: 640 GWh6402025

GWh per year of wind output lost because Terna ordered wind farms to cut output to keep the high-voltage grid secure. Main causes in 2025: congestion 223 GWh, grid works 148, excess generation 188; ARERA gives no cause for the other 81. ARERA annual reports, from Terna data. Solar is counted separately and not included. Sources: 1 2 3

Show data as a table
PeriodRenewable output curtailed
2022301
2023300.7
2024347.5
2025640

Sources behind these areas in this preview coming with the atlas

  • Terna connection requests (in this preview)
  • OpenStreetMap grid (in this preview)

Source: Terna Econnextion, via pv magazine Italia

  • 400 kV
  • 150 kV
  • Region with published figures

Pick a highlighted region on the map, or use the region buttons. Highlighted: regions for which the source publishes figures. Grid: © OpenStreetMap contributors (ODbL). Boundaries: Natural Earth.

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
190.3 MW
With a signed connection contract
52.3 MW
Cancelled
379.2 MW

In Thessaly, twice as much capacity has been cancelled as is still waiting. 268.1 of the 379.2 MW cancelled was dropped after HEDNO told the projects the grid had no room for them.

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
103.4 MW142 projects
With a signed connection contract
55.6 MW79 projects
Cancelled
410.2 MW

In Western Macedonia, 89.7% of the cancelled capacity was dropped after HEDNO told the projects the grid had no room for them.

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
60.2 MW
With a signed connection contract
41.2 MW
Cancelled
733.8 MW

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
55.3 MW
With a signed connection contract
47 MW
Cancelled
201.3 MW

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
16.2 MW
With a signed connection contract
8.2 MW
Cancelled
86.1 MW

In Attica, 63.7 of the 86.1 MW cancelled was dropped after HEDNO told the projects the grid had no room for them.

Energy-community projects on the local distribution grid (HEDNO, low and medium voltage), May 2026

Waiting to connect
59.8 MW
With a signed connection contract
9.5 MW
Cancelled
5.7 MW

Crete has 85 active energy communities. Since May 2025 a 1,000 MW cable from Attica has carried power to the island.

Battery connection applications vs capacityGreece will connect 4.7 GW of batteries that earn their money on the market, without subsidies. Applications reached 12.15 GW, more than twice that. About 9 GW passed the first check (complete paperwork); the ranked lists are expected in October 2026.
Gigawatt (GW)IPTO (transmission)HEDNO (distribution)AppliedIPTO (transmission): 10 GWHEDNO (distribution): 2.15 GW12.15 GWComplete paperworkIPTO (transmission): ≈8 GWHEDNO (distribution): ≈1 GW≈9 GWGrid capacity on offerIPTO (transmission): 3.8 GWHEDNO (distribution): 0.9 GW4.7 GW
Gigawatt (GW)IPTO (transmission)HEDNO (distribution)AppliedIPTO (transmission): 10 GWHEDNO (distribution): 2.15 GW12.15 GWComplete paperworkIPTO (transmission): ≈8 GWHEDNO (distribution): ≈1 GW≈9 GWGrid capacity on offerIPTO (transmission): 3.8 GWHEDNO (distribution): 0.9 GW4.7 GW

Standalone batteries, GW, as reported by pv magazine (March 2026), larissapress (July 2026) and mononews (September 2026); the split of the 9 GW is approximate. Greece publishes its queue as snapshots, not a monthly series: ampear will build that history from its own monthly snapshots. Sources: 1 2 3

Show data as a table
StageIPTO (transmission) (GW)HEDNO (distribution) (GW)Total (GW)
Applied102.1512.15
Complete paperwork≈8≈1≈9
Grid capacity on offer3.80.94.7
Renewable output curtailedCurtailment doubled in 2025. By July 2026 it had almost reached the 2025 total.
Gigawatt-hours (GWh)05001,0001,5002,0002024: 899 GWh89920242025: 1,867 GWh1,86720252026 (January to July): 1,746 GWh1,7462026*
Gigawatt-hours (GWh)05001,0001,5002,0002024: 899 GWh89920242025: 1,867 GWh1,86720252026 (January to July): 1,746 GWh1,7462026*

GWh per year of solar and wind output that was not used because supply exceeded what the system could absorb or export. Estimates by The Green Tank from IPTO data. *2026: January to July. Sources: 1 2

Show data as a table
PeriodRenewable output curtailed
2024899
20251,867
2026 (January to July)1,746

Sources behind these areas in this preview coming with the atlas

  • HEDNO connection files, via The Green Tank (in this preview)
  • The Green Tank analyses of HEDNO and IPTO data (in this preview)
  • OpenStreetMap grid (in this preview)

Source: The Green Tank, from HEDNO data

Reports for a single project

We run your project through the published data and the ampear simulation engine and deliver a report with a fixed scope: curtailment and prices, what a battery earns, and which rule changes move the answer. Every input and assumption is in the report.

  1. Site Used in the sample reports

    A 1 MW solar park in Thessaly, or 20 MWp of solar plus storage in Puglia.

    What do curtailment and low prices cost, and when does a battery pay back?

  2. Network Engine ready

    A business park on three local grid lines, or a municipality spread across several substations.

    Which cables and transformers overload first, and where does flexibility help most?

  3. Region Planned

    Puglia in 2030 if half of today's connection queue gets built.

    How much output could be lost when the region produces more than it can use or export?

Built for

Developers and investors
Screen a project before you commission a full study: queue pressure, curtailment exposure and battery economics, with every source listed.
Park owners and aggregators
See what curtailment and low prices cost an existing solar park, and when adding a battery pays back.
Consultancies and advisors
Sourced figures and a documented model you can check, cite and build on in your own studies.

Reports are indicative, for screening and early due diligence, and are not bankable studies. They complement, and do not replace, your independent advisor. There is no self-serve platform yet: we run the scenarios for you.

Sample reports

Two screening reports on illustrative projects, one per country, coming in October 2026. Every figure carries its source; assumptions and limits have their own section.

To get a copy, sign up for the Friday briefing and we send you both reports when they are out, or write to mo@traect.dev.

The Friday briefing, in the format it will arrive

TypeCountryDateChangeSource
NewIT8 Sep 2026Decree 291 tackles 'virtual saturation': grid capacity reserved by projects that may never be built. Terna must now publish, and update every quarter, how much new renewable capacity each area can still take.MASE
ChangedIT31 Aug 2026Data centre connection requests pass 100 GW: 553 requests for 101.36 GW.Terna, via pv magazine
ChangedIT31 Aug 2026Solar projects waiting to connect: 140.31 GW requested. Only 225 projects (10.26 GW) are ready to build.Terna, via pv magazine
NewIT2026Second MACSE auction, Terna's long-term contracts for new storage: 16 GWh to be awarded, for delivery in 2029.ARERA, via Montel
ChangedGR20 Mar 2026Greek programme for batteries that earn their money on the market, without subsidies: 12.15 GW applied for 4.7 GW of grid capacity.IPTO, HEDNO, via pv magazine

Sample issue built from published figures. Every line links to its source.

What opens, in order

  1. Friday briefing

    Starts first

    One email a week per country: how much new capacity the grid can take, application windows, auctions and rule changes, for Italy and Greece.

  2. Sample reports

    October 2026

    Two screening reports on illustrative projects, one for Greece and one for Italy.

  3. Reports on your project

    Next

    The same report on your own park or project, with a published scope.

  4. Area atlas

    Later

    A public map with a page per region and grid area: how much capacity is waiting to connect, by technology and stage, and how much room is left, with the history. Every figure keeps its source and the date we retrieved it.

  5. Alerts, API and MCP

    Later

    Follow regions and areas and get an email when a rule changes or an application window or auction opens. Query the atlas from your own tools and AI assistants.

Hear it first.

ampear is being built now. Subscribe to the Friday briefing and we will send you the sample reports when they are out.

Subscribe to the Friday briefing

Sources

ampear reports official data, as published by grid operators, regulators and ministries or reported by energy press and analysts: Terna, ARERA and the Ministry of Environment and Energy Security (MASE) in Italy; IPTO, HEDNO, RAAEY and the Government Gazette in Greece; ENTSO-E across Europe; pv magazine, QualEnergia, Montel and The Green Tank where they report a figure. It links to the originals and is not investment, legal or engineering advice.

We keep only your email address, language, the page you signed up on, signup and confirmation dates and the random codes in our email links, to send the Friday briefing. How we use your email